项目描述
This project incorporates the design and construction of new turn lanes and traffic signal modifications at various intersections in Port Charlotte, 佛罗里达. New left and right turn lanes will be added to various intersections along with possible signal modifications, 人行道上, and pedestrian crosswalk improvements.
项目位置
- Cochran Boulevard @ Quesada Avenue – Northbound right turn on Quesada Avenue
- Murdock Circle @ US Highway 41 – Eastbound right turn lane on Murdock Circle
- Peachland Boulevard @ Harbor Boulevard - Left turn lanes on all approaches
- Veterans Boulevard @ Cochran Boulevard – East and Westbound right turn lanes on Veterans Boulevard, Northbound Right turn lane
- Veterans Boulevard @ Atwater Street – East and Westbound right turn lanes
- Veterans Boulevard @ Yorkshire Street – East and Westbound right turn lanes
- Veterans Boulevard @ Harbor Boulevard – East and Westbound right turn lanes
- Veterans Boulevard @ Orlando Boulevard – Eastbound right turn lane
- Veterans Boulevard @ Torrington Street – Eastbound right turn lane
- Veterans Boulevard @ Loveland Boulevard – Eastbound right turn lane
项目的影响
Due to the Hurricane, the scheduled has been delayed.最新的更新
Cochran Boulevard @ Quesada Avenue – Northbound right turn on Quesada Avenue (completed)
Murdock Circle @ US Highway 41 – Eastbound right turn lane on Murdock Circle (completed)
Veterans Boulevard @ Cochran Boulevard intersection. 90% plans have been reviewed by Charlotte County staff and returned to FTE for updates. Final plans are due on March 04, 2024
Veterans Boulevard @ Torrington Street intersection. 90% plans have been reviewed by Charlotte County staff and returned to FTE for updates
Veterans Boulevard @ Loveland Boulevard intersection. 90% plans have been reviewed by Charlotte County staff and returned to FTE for updates
Peachland Boulevard @ Harbor Boulevard intersection. 设计 survey has started. 60% plans are due for review on October 18, 2024
Veterans Boulevard @ Atwater Street intersection. 设计 survey has started. 60% plans are due for review on June 06, 2024
Veterans Boulevard @ Yorkshire Street intersection. 90% plans are currently being reviewed by county staff.
Veterans Boulevard @ Harbor Boulevard intersection. 60% plans have been reviewed by Charlotte County staff and returned to FTE for updates. 90% plans are due for review on March 28, 2024
Veterans Boulevard @ Orlando Boulevard intersection. 设计 survey has started. 60% plans are due for review on April 4, 2024
预算
阶段 | 成本 |
---|---|
设计 | $1,524,234.50 |
建设 | $1,000,000.00 |
总预算 | $2,524,234.50 |
汽油税C411620
国家资助补助金
时间表
阶段 | 预计开始日期 | 预计完成 | 实际完成 |
---|---|---|---|
Planning and Approval | 02/11/2019 | 08/14/2019 | 08/14/2019 |
设计开发 | 09/02/2020 | 12/13/2023 | |
建设 | 04/17/2024 | 02/10/2025 |
支持材料
项目阶段
设计开发
最后一次更新
03/25/2024
项目经理
杰夫大尺度
公共关系
特蕾西·多尔蒂
Email 公共关系
项目数量
19-279
支持部门
公共工程
设计 Engineer/Architect
佛罗里达 Transportation Engineering
建设 Contractor
TBD